Section 50 licence application guidance notes

Grant of licence

Extract from Schedule 3

New Roads and Street Works Act 1991

Grant of licence

Before granting a Street Works Licence the Street Authority will give no less than ten working days' notice to each of the following: 

(a) where the works are likely to affect a public sewer, to the Sewer Authority

(b) where the works are to be executed in a part of a street which is carried or crossed by a bridge vested in a transport authority, or crosses, or is crossed by any other property held or used for the purposes of a transport authority, to that

(c) where in any other case the part of the street in which the works are to be executed is carried or crossed by a bridge, to the bridge authority

(d) to any person who has given notice under section 54 (advance notice of certain works) of his intention to execute street works which are likely to be affected by the works, and

(e) to any other person having apparatus in the street which is likely to be affected by the works