Street Works Permit Scheme Review

Executive Summary

The Traffic Management Act 2004 (TMA) was introduced to address congestion and disruption on highway networks, providing legislative support for highway authorities to implement permit schemes. Stockton-on-Tees Borough Council adopted its Permit Scheme on 30 March 2020 to enhance co-ordination and minimise disruption caused by street works and road works. 

Key objectives

Some of the key objectives being to:

  • minimise disruption on the local highway networks
  • provide accurate, timely information to stakeholders
  • facilitate proactive and collaborative planning
  • ensure parity between internal (Council) and external works promoters

Key highlights for Year 4

Permit applications

Total number of permit applications and variations received: 4,397

Percentage of applications assessed within permitted timescales: 100%

Financial overview

The scheme continued to operate at a deficit, primarily due to increased staffing costs associated with agreed pay settlements.